TOE END STABILISATION

BUNN LEISURE

Client

£1.35M

Value

The Project Details

Demolition of existing timber groynes and rock revetment. Supply and place 14,500t of rock armour on geotextile membrane imported from norway to form new revetment. Construction of new timber groynes, wave wall and all associated works.

This Contract Included:

  • Supply, deliver and place 14,500t of 5-8t and 3-6t Norwegian armour stone for new revetment
  • Tranship offshore ship to barge and to beach
  • Transport from quayside in Southampton docks to selsey bill in 500t loads using 50m rock barge and tug combination
  • Our own 50t excavator handling the stones onboard delivery at high tide